CONSTRUCTION AND DEVELOPMENT

Business centre in Saint Petersburg

Location

YAROVIT Holding continues its production and development business in the city of Saint Petersburg. In direct proximity to the “Yarovit Motors” assembly factory , the company bought an unfinished building which will be reconstructed to serve as a multifunctional business-centre. The facility is located in the Kalininsky District of Saint Petersburg at the crossing of Feodossiyskaya and Zhukov Streets, not far from Sverdlovskaya Quya. The edifice central façade runs along Feodossiyskaya Street.

Design

The design is performed by the company “Tradition” Architectural Office Ltd.” of Saint Petersburg. At present, the “Project” stage has been completed and all required pre-project approvals have been received.

 

Architect’s concept of the business center in Saint Petersburg

Technical and economic data:
 

1. Lot area— 4154 m2

2. Number of levels— 10.

3. Total space of the building— 15.623,7 m2

4. Total rentable space— 12.279,2 m2

5. Ground floor — 1,797.8 m2

6. Standard floor (2, 3, 4, 5, 6, 7, 8, 9 levels)— 1350.5 m2

7. 10th (service) floor area— 347.8 .2

8. Mezzanine service floor— 673.9 m2

9. Basement area, with the parking entrance-exit pavilion— 2.000,3 m2

10. Underground parking— 40 lots;

11. Surface parking on adjacent territory— 42 lots.
 
Functional purpose of the facility
 
Class B office centre with trading and service infrastructure elements.
The following accommodations are envisaged as parts of the facility:
 

· Car sale and exhibition show— 1 246.4 sq.m;

· Underground parking for 40 vehicles— 1 965 sq.m;

· 50-seat cafe— 332.4 sq.m;

· Service floor— 673.9 sq.m;

· Standard office floor (2,3,4,5,6,7,8,9)- 10 804 sq.m;

· Office floor No 10— 347.8 sq.m;

Office rooms with the aggregate space of 7 536 sq.m are designed to be transformable to satisfy individual convenient layout and modern design preferences. The adjacent territory will accommodate a 42-vehicle open-air parking. There is a breath-taking view on the Neva river and the Smolny Palace from the top floors and the access balcony. The building is located within a 15-minute ride from the centre of Saint Petersburg.
 
Life-support system solutions
 
The building design stipulates for: central HVAC, standby emergency electric generator, modern telecommunication system providing unlimited number of digital communication lines, high speed Internet for every office, noiseless high-speed “OTIS” elevators. Monitoring is performed byusing a modern Building Monitoring System (BMS).
Within an open tender, the JSC “StroyComplex XXIst Century” has been selected as the general contractor for the reconstruction of the unfinished building into a business centre.

Facility commissioning date— 2nd quarter of 2007.
 
To ask questions, address: development@yarovit.com